12
contractor for the subcontractor’s negligence. Montara Owners Association v. La Noue
Development LLC et al., 357 Or, 333 (2015).
Finally, the duty to indemnify is independent from the duty to defend. Ledford v.
Gutoski, 319 Or. 397, 403, 877 P.2d 80, 84 (Or. 1994). Oregon courts note that the
failure to defend does not create a duty to indemnify the insured by estoppel. Nw.
Pump & Equip. Co. v. Am. States Ins. Co., 144 Or. App. 222, 227, 925 P.2d 1241, 1243
(Or. Ct. App. 1996). See discussion infra Duty to Defend. The duty to defend under an
indemnity agreement is triggered in the same manner and to the same extent as the
duty to defend under an insurance policy. St. Paul Fire & Marine v. Crosetti Bros., 256
Or 576, 580 (1970); National Union Fire Ins. Co. v. Starplex Corp., 220 Or App 560, 572-
74 (2008). Thus, the “defend-one defend-all” rule generally applies. However, ORS
30.140’s restrictions on provisions that require one person to “indemnify” another for
that person’s own negligence apply equally to agreements requiring a person to defend
another. Sunset Presbyterian Church v. Andersen Construction Company, 286 Or App
309 (2014). Thus, a general contractor seeking post-resolution defense fees from a
subcontractor pursuant to an agreement to “indemnify and hold harmless” bears the
burden of allocating its defense costs in accordance with ORS 30.140. Id.
Rains v. Stayton Builders Mart, Inc., 264 Or. App. 636, 336 P.2d 483 (2014), rev
allowed, 357 Or. 111 (2015), held that a claim remains justiciable even after the plaintiff
and one of the defendants agreed to a floor and ceiling amount of damages if the
defendant was found liable. On appeal, the other defendant argued that there was no
longer a controversy because the co-defendant had an incentive to be found liable and
then pursue indemnity. The court disagreed because the agreement between that co-
defendant and plaintiff did not establish exposure. Unless or until a party has “’no
interest’ in the outcome of a case because it could ‘neither gain nor lose anything as a
result of trial,’” a justiciable controversy remained. Id. at 646.
X. STATUTE OF LIMITATIONS
The statute of limitations for contract actions is six years from the time the cause
of action accrues. ORS 12.080(1). A breach of contract claim accrues from the time of the
breach (usually occurring when construction is completed), even if the breach is not
discovered until much later. Waxman v. Waxman & Associates, Inc., 224 Or App 499, 510,
198 P 3d 445 (2008). However, based on a case construing an adjacent sub-section of
ORS 12.080, some trial courts have held that the six year period for breach of contract
claims runs from the discovery of the breach. See Rice v. Rabb, 354 Or 721 (2014).
Tort claims alleging property damage resulting from faulty construction must be
brought within two years of the date that the cause of action accrues, ORS 12.110, subject
to the statute of ultimate repose. Goodwin v. Kingsmen Plastering, 359 Or 694 (2016).
Such claims accrue when the plaintiff discovers or should have discovered damage caused